Manual Activity Sheet (Schedule Types)
The following explains each of the manual activity sheet Schedule types:
Duration Based Schedules
- The manual Activity Sheet receives duration based information from P6 only through XML import
- The manual Activity Sheet is available as a source for Cash Flow
- The manual Activity Sheet does not have any cost related feature (Assign rate sheet and Recost)
- The manual Activity Sheet is not available for Earned Value Analysis