Auto-Scheduling

If the user clicks on Update > Linked Schedule Sheets, then only the Activity Data will get updated on the destination (linked) Schedule Sheets from the template, and not the sheet properties.

When auto-scheduling is disabled, if you push dates to the Master Schedule Sheet from Program Activity Sheet, then you can update changes for a particular activity, but there will be no impact of your changes reflected in dependent activities. Also, since the Master Schedule Sheet is updated by Program Activity Sheet, a Refresh icon appears in the log, next to the title.



Last Published Monday, August 28, 2023