Schedule Sheet Integration
Unifier supports out of the box (OOTB) mapping for integration between P6 and Unifier, using Schedule Sheets.
This OOTB mapping is available as part of Project Control installation as a shell template (T-002). You must create a new shell by copying shell template (T-002) in order to integrate P6 and Unifier using Schedule Sheets.
To view the data mapping fields in Unifier:
- Go to Company Workspace > Admin mode > Templates > Shells > Projects.
- Open the T-002 (Project #) Owner Project Template(Project Name).
- From the left-hand navigator, click Schedule Manager > Schedule Sheets.
- In the Schedule Sheets log, open Project Schedule Sheet.
- From the menu bar, click File > Data Mappings.
- Click P6 (to select) > Modify > Activity tab.
The column name and XML elements are listed as shown below. You can use the XML elements for integration with P6.
Column | XML Element |
---|---|
Activity Name | Name |
Activity Percent | PercentComplete |
Actual Finish Date | ActualFinishDate |
Actual Start Date | ActualStartDate |
Duration | PlannedDuration |
Early Start date | EarlyStartDate |
Early finish date | EarlyFinishDate |
Finish date | PlannedFinishDate |
Late Start date | LateStartDate |
Late finish date | LateFinishDate |
P6 Activity Number | Id |
P6 CBS | CBSCode |
Start date | PlannedStartDate |