Create an Activity Sheet
The permissions for creating an Activity Sheet are the same as those for creating a Schedule Sheet. You can create a new sheet or use a template.
To create an activity sheet
- Navigate to your shell in User mode and click the Schedule Manager grouping node to expand.
- Click Activity Sheet.
- Click Create. The Activities Sheet properties window opens.
- Complete the General block as needed.
- Complete the Activity Sequence Numbering block as needed.
To complete the General block:
In this field | Do this |
---|---|
Name | Enter a name for the sheet. This is used as the sheet identifier and must be unique. (up to 120 characters) |
Description | Enter an optional description. (up to 400 characters) |
Status | When you are ready to make the sheet active and available for use, click Active. The default is Active. |
Calendar | Select the type of calendar that will be used for the activities in the sheet. |
Select Project Schedule Start Date Source | Select Manual if you would like to manually set a start date for the schedule. If you select From Shell Attribute, this field becomew read only and auto-populates with the start date defined in Shell Properties. |
Schedule Start Date | If you selected Manual in the Select Project Schedule Start Date Source field, this field will become editable, and you can input the desired start date for the schedule. |
Time Zone | Select the time zone that will be used when saving the date and time of activities in the sheet. |
Data Date | This field is auto-populated with the current date and read only. |
Schedule Type | This field is auto-populated and read only. |
To complete the Activity Sequence Numbering block:
In this field | Do this |
---|---|
Activity ID Prefix | When creating an activity in the activity sheet, the Activity ID will start with the alphanumeric characters in this field. |
Activity ID Suffix | When creating an activity in the activity sheet, the Activity ID will end with the number in this field. |
Increment | When creating an activity in the activity sheet, the number in the Activity ID will increase by this number from the highest Activity ID number in the log. |
See Also
Activity Sheets in Schedule Manager
Update Activity Sheet Properties
Set up Activity Sheet Baselines