BaselineProjectUpdated Message

Field

Type

Description

Id

string

The short code assigned to each WBS element for identification. Each WBS element is uniquely identified by concatenating its own code together with its parents' codes.

Name

string

The name of the baseline project.

ObjectId

int

The unique ID generated by the system.

NewValues

BaselineProjectType

Refer to the entries in the BaselineProjectType Table below.

Additional information can be found in the p6events.xsd schema.

The new values of Physical and writable fields that have changed.

OldValues

BaselineProjectType

Refer to the entries in the BaselineProjectType Table below.

Additional information can be found in the p6events.xsd schema.

The old values of Physical and writable fields that have changed.

BaselineProjectType Table

Type: BaselineProjectType

Elements

Type

ActivityDefaultActivityType

string
restricted to
'Task Dependent'
'Resource Dependent'
'Level of Effort'
'Start Milestone'
'Finish Milestone'
'WBS Summary'

ActivityDefaultCalendarObjectId

int

ActivityDefaultCostAccountObjectId

int

ActivityDefaultDurationType

string
restricted to
'Fixed Units/Time'
'Fixed Duration and Units/Time'
'Fixed Units'
'Fixed Duration and Units'

ActivityDefaultPercentCompleteType

string
restricted to
'Physical'
'Duration'
'Units'

ActivityDefaultPricePerUnit

double

ActivityIdBasedOnSelectedActivity

boolean

ActivityIdIncrement

int

ActivityIdPrefix

string

ActivityIdSuffix

int

ActivityPercentCompleteBasedOnActivitySteps

boolean

AddActualToRemaining

boolean

AddedBy

string

AllowStatusReview

boolean

AnnualDiscountRate

double

AnticipatedFinishDate

dateTime

AnticipatedStartDate

dateTime

AssignmentDefaultDrivingFlag

boolean

AssignmentDefaultRateType

string
restricted to
'Price / Unit'
'Price / Unit 2'
'Price / Unit 3'
'Price / Unit 4'
'Price / Unit 5'

BaselineTypeObjectId

int

CostQuantityRecalculateFlag

boolean

CriticalActivityFloatLimit

double

CriticalActivityPathType

string
restricted to
'Critical Float'
'Longest Path'

DateAdded

dateTime

DefaultPriceTimeUnits

string
restricted to
'Hour'
'Day'
'Week'
'Month'
'Year'
'Days Hours'
'Hours Minutes'

Description

string

DiscountApplicationPeriod

string
restricted to
'Month'
'Quarter'
'Year'

EnablePublication

boolean

EnableSummarization

boolean

FiscalYearStartMonth

int

HistoryInterval

string
restricted to
'Month'
'Week'
'Quarter'
'Year'
'Financial Period'

HistoryLevel

string
restricted to
'None'
'Project'
'WBS'
'Activity'

Id

string

IndependentETCLaborUnits

double

IndependentETCTotalCost

double

LastBaselineUpdateDate

dateTime

LastFinancialPeriodObjectId

int

LastUpdateBaselineOptions

string

LevelingPriority

int

LinkActualToActualThisPeriod

boolean

LinkPercentCompleteWithActual

boolean

LinkPlannedAndAtCompletionFlag

boolean

LocationObjectId

int

MustFinishByDate

dateTime

Name

string

OBSObjectId

int

ObjectId

int

OriginalBudget

double

OwnerResourceObjectId

int

ParentEPSObjectId

int

PlannedStartDate

dateTime

PrimaryResourcesCanMarkActivitiesAsCompleted

boolean

ProjectForecastStartDate

dateTime

PublicationPriority

int

ResetPlannedToRemainingFlag

boolean

ResourceCanBeAssignedToSameActivityMoreThanOnce

boolean

ResourcesCanAssignThemselvesToActivities

boolean

ResourcesCanEditAssignmentPercentComplete

boolean

RiskMatrixObjectId

int

ScheduledFinishDate

dateTime

Status

string
restricted to
'Planned'
'Active'
'Inactive'
'What-If'
'Requested'
'Template'

StatusReviewerObjectId

int

StrategicPriority

int

WBSCodeSeparator

string

WebSiteRootDirectory

string

WebSiteURL

string



Legal Notices | Your Privacy Rights
Copyright © 2010, 2023

Last Published Tuesday, February 28, 2023