ProjectResource Service

Operations:

CreateProjectResources Operation

ReadProjectResources Operation

UpdateProjectResources Operation

DeleteProjectResources Operation

GetFieldLengthProjectResource Operation

WSDL: ProjectResource.wsdl

Primary Key Field: ObjectId

Target Namespace: http://xmlns.oracle.com/Primavera/P6/WS/ProjectResource/V1

Default Transport URLs:

http://<hostname>:<port number>/p6ws/services/ProjectResourceService?wsdl

https://<hostname>:<port number>/p6ws/services/ProjectResourceService?wsdl

Java Client Stub Class:

com.primavera.ws.p6.projectresource.ProjectResourceService

Description:

Primavera's resource planning feature allows you to do high-level project planning for future project or project that does not require resource assignments at the activity level. The resource planning feature allows you to allocate and manage resources at the project and WBS levels. If the LifeOfProjectFlag is true, the resource assignment is for the duration of the project, and so, if the project dates are pushed out, the resource assignment dates are pushed as well.

If the LifeOfProjectFlag is false, the dates on the ProjectResource will be calculated from the dates on the child ProjectResourceQuantity objects.