Description: This operation copies the activity to a project or a WBS. The WBS can be in the current project or in a different project. If both the project ObjectId and the WBS ObjectId are specified, the WBS ObjectId will take precedence.
Service: Activity Service
Style: Document/literal wrapped
Input:
Message: CopyActivity
Elements:
- ObjectId
- TargetProjectObjectId
- TargetWBSObjectId
- TargetActivityId
- CopyResourceAndRoleAssignments
- CopyRelationships
- CopyActivityCodes
- CopyActivityNotes
- CopyActivityExpenses
- CopyActivitySteps
- CopyProjectDocuments
- CopyPastPeriodActuals
Required fields You must supply the ObjectId and at least one of the following fields when you use the CopyActivity operation:
- TargetProjectObjectId
- TargetWBSObjectId
All other fields are optional.
Output:
Message: CopyActivityResponse
Elements: An ObjectId representing the unique identifier of the new activity.