ActivityStep Fields


 Field


 Type

Read 
Only

Filterable
Orderable


 Description

ActivityId

string
restricted to
maxLength(40)

X

X

The short ID that uniquely identifies the activity within the project.

ActivityName

string
restricted to
maxLength(120)

X

X

The name of the activity. The activity name does not have to be unique.

ActivityObjectId

int

 

X

The unique ID of the activity to which the steps are assigned.

CreateDate

dateTime

X

X

The date this activity step was created.

CreateUser

string
restricted to
maxLength(255)

X

X

The name of the user that created this activity step.

Description

string

 

 

The description of the activity step.

IsBaseline

boolean

X

X

The boolean value indicating if this business object is related to a Project or Baseline.

IsCompleted

boolean

 

X

The flag that indicates whether the step has been completed.

IsTemplate

boolean

X

X

The boolean value indicating if this business object is related to a template Project.

LastUpdateDate

dateTime

X

X

The date this activity step was last updated.

LastUpdateUser

string
restricted to
maxLength(255)

X

X

The name of the user that last updated this activity step.

Name

string
restricted to
maxLength(120)

 

X

The name of the activity step.

ObjectId

int

 

X

The unique ID generated by the system.

PercentComplete

double
restricted to
minInclusive(0.0)
maxInclusive(1.0)

 

X

The percent complete for the step.

ProjectId

string
restricted to
maxLength(40)

X

X

The short code that uniquely identifies the project.

ProjectObjectId

int

X

X

The unique ID of the associated project.

SequenceNumber

int

 

X

The sequence number for sorting.

WBSObjectId

int

X

X

The unique ID of the WBS for the activity.

Weight

double
restricted to
minInclusive(0.0)
maxInclusive(999999.0)

 

X

The weight that is assigned to the step. This is a user defined field that is used to calculate the physical percent complete when the project option is set.

WeightPercent

double

X

 

The non-editable field that displays the percentage amount that corresponds to the step. It is calculated by taking the weight of the step and dividing it by the total of all weights for the activity.