ResourceRate Fields


 Field


 Type

Read 
Only

Filterable
Orderable


 Description

CreateDate

dateTime

X

X

The date this resource rate was created.

CreateUser

string
restricted to
maxLength(255)

X

X

The name of the user that created this resource rate.

EffectiveDate

dateTime

 

X

The effective date for the resource price and maximum units per time.

LastUpdateDate

dateTime

X

X

The date this resource rate was last updated.

LastUpdateUser

string
restricted to
maxLength(255)

X

X

The name of the user that last updated this resource rate.

MaxUnitsPerTime

double
restricted to
minInclusive(0.0)

 

X

The maximum work units per time this resource can perform on all their assigned activities. For example, a person working full time could perform 8 hours of work per day. A department of five people may perform at 5 days per day.

ObjectId

int

 

X

The unique ID generated by the system.

PricePerUnit

double
restricted to
minInclusive(0.0)
maxInclusive(9.99999999999999E12)

 

X

The non-overtime price per time for the resource. This price is used to compute costs for any activities the resource is assigned to. In general, cost = units * price per time.

PricePerUnit2

double
restricted to
minInclusive(0.0)
maxInclusive(9.99999999999999E12)

 

X

The non-overtime price per time for the resource. This price is used to compute costs for any activities the resource is assigned to. In general, cost = units * price per time.

PricePerUnit3

double
restricted to
minInclusive(0.0)
maxInclusive(9.99999999999999E12)

 

X

The non-overtime price per time for the resource. This price is used to compute costs for any activities the resource is assigned to. In general, cost = units * price per time.

PricePerUnit4

double
restricted to
minInclusive(0.0)
maxInclusive(9.99999999999999E12)

 

X

The non-overtime price per time for the resource. This price is used to compute costs for any activities the resource is assigned to. In general, cost = units * price per time.

PricePerUnit5

double
restricted to
minInclusive(0.0)
maxInclusive(9.99999999999999E12)

 

X

The non-overtime price per time for the resource. This price is used to compute costs for any activities the resource is assigned to. In general, cost = units * price per time.

ResourceId

string
restricted to
maxLength(20)

X

X

The short code that uniquely identifies the resource.

ResourceName

string
restricted to
maxLength(100)

X

X

The name of the resource.

ResourceObjectId

int

 

X

The unique ID of the associated resource.

ShiftPeriodObjectId

int

 

X

The unique ID of the associated shift.