Update CBSDurationSummarys
put
/cbsDurationSummary
Send a request to this endpoint to update one or more cbsDurationSummary. For each JSON object provided in the request body, an application object with a matching ID value will be updated to reflect the JSON contents.
Request
Header Parameters
-
Authorization(required):
OAuth token
Supported Media Types
- application/json
A list of cbsDurationSummary objects.
Root Schema : List<CBSDurationSummary>
Type:
array
Title:
Show Source
List<CBSDurationSummary>
-
Array of:
object CBSDurationSummary
Title:
CBSDurationSummary
CBSDurationSummary Entity
Nested Schema : CBSDurationSummary
Type:
object
Title:
CBSDurationSummary
CBSDurationSummary Entity
Show Source
-
CBSObjectId(required): integer
(int32)
The internal CBS ID of the project. This ID cannot be used to load the CBS object directly.
-
OriginalProjectObjectId: integer
(int32)
The unique ID of the project from which the project baseline was created, if the current project is a project baseline
-
ProjectId(required): string
The short code of the associated project.
-
ProjectName: string
The name of the associated project.
-
ProjectObjectId: integer
(int32)
The unique ID of the associated project.
-
SummaryActualDuration: number
(double)
The actual duration.
-
SummaryActualFinishDate: string
(date-time)
The latest actual finish date of all activities in the CBS.
-
SummaryActualStartDate: string
(date-time)
The earliest actual start date of all activities in the CBS.
-
SummaryPercentComplete: number
(double)
The measure that indicates how much of the CBS baseline duration has been completed so far. Computed based on where the current data date falls between the activity's baseline start and finish dates. If the data date is earlier than the baseline start, the schedule % complete is 0. If the data date is later than the baseline finish, the schedule % complete is 100. The schedule % complete indicates how much of the CBS duration should be currently completed, relative to the selected baseline.
-
SummaryPlannedDuration: number
(double)
The total working days between planned start and finish dates in the CBS.
-
SummaryPlannedFinishDate: string
(date-time)
The latest planned finish date of all activities in the CBS.
-
SummaryPlannedStartDate: string
(date-time)
The earliest planned start date of all activities in the CBS.
-
SummaryRemainingDuration: number
(double)
The total working time from the CBS remaining start date to the remaining finish date.
-
SummaryRemainingFinishDate: string
(date-time)
The date the resource is scheduled to finish the remaining work for the activity.
-
SummaryRemainingStartDate: string
(date-time)
The earliest remaining start of all activities assigned to the CBS.
Response
Supported Media Types
- application/json
200 Response
OK.
Root Schema : schema
Type:
boolean
400 Response
Bad Request.
401 Response
Unauthorized.
403 Response
Forbidden.
404 Response
Not Found.
405 Response
Invalid Input.
500 Response
Internal Server Error.