P6 EPPM Field | P6 EPPM Table Field | P6 EPPM Table | MPX Field |
---|---|---|---|
Project Name/WBS Name | wbs_name | PROJWBS | Project tab |
n/a | defaults to empty string | n/a | Company |
User Defined Field Title | User Defined Field (Exchanged only if a mapping is defined for the field.) | UDFVALUE | Manager |
The default project calendar is exported. | defaults to Standard | n/a | Calendar (Standard used if no entry) |
Data Date | data_date | PROJECT | Start Date (either this field or the Finish Date field is calculated for an imported file, depending on the Schedule From setting) |
Must Finish By | plan_end_date | PROJECT | Finish Date (Calculated by P6 EPPM.) |
n/a | defaults to 0 | n/a | Schedule From |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Current Date (Calculated by P6 EPPM.) |
Notebook Description | wbs_memo | WBSMEMO | Comments |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Cost (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Baseline Cost (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Actual Cost (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Work (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Baseline Work (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Actual Work (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Work (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Duration (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Baseline Duration (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Actual Duration (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Percent Complete (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Baseline Start (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Baseline Finish (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Actual Start (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Actual Finish (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Start Variance (Calculated by P6 EPPM.) |
n/a | calculated by Microsoft Project (defaults to empty string) | n/a | Finish Variance (Calculated by P6 EPPM.) |
User Defined Field Title | User Defined Field (Exchanged only if a mapping is defined for the field.) | UDFVALUE | Subject |
User Defined Field Title | User Defined Field (Exchanged only if a mapping is defined for the field.) | UDFVALUE | Keywords |