MPX Field | P6 EPPM Table Field | P6 EPPM Table | P6 EPPM Field |
---|---|---|---|
ID | rsrc_id | TASKRSRC | Resource ID Name |
Units | target_qty_per_hr | TASKRSRC | Planned Units/Time (P6 EPPM) Budgeted Units/Time or Planned Units/Time (P6 Professional) |
Work | total_qty | TASKRSRC | At Completion Units |
Planned Work | target_qty | TASKRSRC | Planned Units (P6 EPPM) Budgeted Units or Planned Units (P6 Professional) |
Actual Work | act_reg_qty | TASKRSRC | Actual Regular Units |
Overtime Work | act_ot_qty | TASKRSRC | Actual Overtime Units |
Cost | total_cost | TASKRSRC | At Completion Cost |
Planned Cost | target_cost | TASKRSRC | Planned Cost (P6 EPPM) Budgeted Cost or Planned Cost (P6 Professional) |
Actual Cost | act_cost | TASKRSRC | Actual Cost |
Start (Calculated by Microsoft Project) | start_date | TASKRSRC | Start |
Finish (Calculated by Microsoft Project) | end_date | TASKRSRC | Finish |
Assignment Delay | lag_drtn_hr_cnt | TASKRSRC | Lag |