P6 EPPM Field | P6 EPPM Column Name |
---|---|
ann_dscnt_rate_pct | Annual Discount Rate |
anticip_end_date | Anticipated Finish |
anticip_start_date | Anticipated Start |
dscnt_period_type | Discount Application Period |
est_wt | Est Weight (P6 Professional only) |
ev_compute_type | Earned Value Percent Complete Technique |
ev_etc_compute_type | Earned Value Estimate-to-Complete Technique |
ev_etc_user_value | Earned Value Performance Factor |
ev_user_pct | Earned Value Percent Complete |
guid | Global Unique ID |
indep_remain_total_cost | Independent ETC Total Cost |
indep_remain_work_qty | Independent ETC Labor Units |
obs_id | Responsible Manager |
orig_cost | Original Budget |
parent_wbs_id | Parent WBS |
phase_id | WBS Category |
proj_id | Project |
proj_node_flag | Project Node |
seq_num | Sort Order |
status_code | Project Status |
status_reviewer | User Reviewing Status |
sum_data_flag | Contains Summary Data |
tmpl_guid | Methodology Global Unique ID |
wbs_id | Unique ID |
wbs_name | WBS Name |
wbs_short_name | WBS Code |