P6 EPPM Field | P6 EPPM Column Name |
---|---|
act_end_date | Actual Finish |
act_equip_qty | Actual Nonlabor Units |
act_start_date | Actual Start |
act_this_per_equip_qty | Actual This Period Nonlabor Units |
act_this_per_work_qty | Actual This Period Labor Units |
act_work_qty | Actual Labor Units |
auto_compute_act_flag | Auto Compute Actuals |
clndr_id | Calendar |
complete_pct_type | Percent Complete Type |
create_date | Added Date |
create_user | Added By |
cstr_date | Primary Constraint Date |
cstr_date2 | Secondary Constraint Date |
cstr_type | Primary Constraint |
cstr_type2 | Secondary Constraint |
driving_path_flag | Longest Path |
duration_type | Duration Type |
early_end_date | Early Finish |
early_start_date | Early Start |
est_wt | Est Weight (P6 Professional only) |
expect_end_date | Expected Finish |
external_early_start_date | External Early Start |
external_late_end_date | External Late Finish |
float_path | Float Path |
float_path_order | Float Path Order |
free_float_hr_cnt | Free Float |
guid | Global Unique ID |
late_end_date | Late Finish |
late_start_date | Late Start |
location_id | Activity Location |
lock_plan_flag | Lock Remaining |
phys_complete_pct |
|
priority_type | Activity Leveling Priority |
proj_id | Project |
reend_date | Remaining Early Finish |
rem_late_end_date | Remaining Late Finish |
rem_late_start_date | Remaining Late Start |
remain_drtn_hr_cnt | Remaining Duration |
remain_equip_qty | Remaining Nonlabor Units |
remain_work_qty | Remaining Labor Units |
restart_date | Remaining Early Start |
resume_date | Resume Date |
rev_fdbk_flag | New Feedback |
review_end_date | Review Finish (P6 Professional only) |
review_type | Review Status (P6 Professional only) |
rsrc_id | Primary Resource |
status_code | Activity Status |
suspend_date | Suspend Date |
target_drtn_hr_cnt | Planned Duration (P6 EPPM) Original or Planned Duration (P6 Professional) |
target_end_date | Planned Finish |
target_equip_qty | Planned Nonlabor Units (P6 EPPM) Budgeted or Planned Nonlabor Units (P6 Professional) |
target_start_date | Planned Start |
target_work_qty | Planned Labor Units (P6 EPPM) Budgeted or Planned Labor Units (P6 Professional) |
task_code | Activity ID |
task_id | Unique ID |
task_name | Activity Name |
task_type | Activity Type |
tmpl_guid | Methodology Global Unique ID |
total_float_hr_cnt | Total Float |
update_date | Last Modified Date |
update_user | Last Modified By |
wbs_id | WBS |