To place or remove a hold on status updates:
- Click Approvals.
- On the Approvals navigation bar, select Status Updates.
- On the Status Updates page:
- To place a hold:
- Select Pending.
- On the status update card, select Hold.
- To remove a hold:
- Select Held.
- On the status update card, select Remove hold.
- To place a hold:
Tips
- Pending updates for a project checked out in P6 Professional or opened exclusively are not displayed until the project is checked in or the exclusive lock is released.
- Team members can continue to make updates to activities that have not been approved yet or are on hold. The status updates will reflect the latest team member updates.