Summarized, Published, and Live Data Usage in P6

The data you see in P6 can be of the following types:

The following table shows which type of data is used in each area of the software.

Dashboards

Data Type

Source

Bubble charts, histograms, pie charts, score cards, side-by-side histograms, stacked histograms.

Published

  • Except costs, units, dates, durations calculated using dates, and activity counts.

Summarized

Project Performance

Published

  • Except earned value management calculations.

Summarized

Open Requests for Resources

 

  • Roles to be staffed

Live

  • Spread data

Published

My Projects

Live

My Activities

Live

My Risks

Live

My Issues

Live

My Documents

Live

My Calendar

Live

Portfolios

Data Type

Source

Portfolio Analysis Page

Published

  • Except costs, units, dates, durations calculated using dates, and activity counts.

Summarized

Capacity Planning Page

Summarized

Performance Status Page

Published

  • Except earned value management calculations.

Summarized

Projects

Data Type

Source

EPS Page

Live

  • Except costs, units, dates, and activity counts.

Summarized

  • Except durations.

Live (but calculated from summarized data)

Activities Page

Live

  • Except Resource Availability.

Published

Team Usage Page

Published

Assignments Page

Live

  • Except Resource Availability

Published

Issues Page

Live

Documents Page

Live

Risks Page

Live

Resources

Data Type

Source

Assignments Page

Live

  • Except Resource Availability

Published

Planning Page

Live

  • Except Resource Availability

Published

Analysis Page

Published

Administration Page

Live

Approvals

Data Type

Source

Status Updates Page

Live

Timesheets Page

Live

Reports

Data Type

Source

All data

Published

Related Topics

Reference Topics

P6 Team Member Interface Field Names

Action Required for Document Reviews Toolbar

Action Required for Workflows Toolbar

Activity Count Columns of the Activity Table

Activity Steps Columns of the Activity Table

Applying Actuals Based on the Auto Compute Actuals Method

Applying Actuals Based on the Timesheets Method

Available Columns of the Activities Page

Available Columns of the Assignments Detail Window of the Activities Page

Available Columns of the Assignments Page

Available Columns of the EPS Page

Baseline Columns of the EPS Table

Bubble Chart Settings Area

Budget Columns of the EPS Table

Calendar Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Cost Columns of the EPS Table

Costs Columns of the Activity Table

Costs Columns of the Assignments Table

Dates Columns of the Activity Table

Dates Columns of the Assignments Table

Dates Columns of the EPS Table

Default Settings for Views

Document Search Criteria

Document Security (Reference)

Durations Columns of the Activity Table

Durations Columns of the Assignments Table

Durations Columns of the EPS Table

Earned Value Columns of the Activity Table

Earned Value Columns of the EPS Table

Errors Section of the Leveling Report Log

Future Period Planning: Deleting, Copying, Pasting, and Replacing Data

Future Period Planning: Entering and Editing Data

Future Period Planning: Importing and Exporting Data

Future Period Planning: Miscellaneous Information

Future Period Planning: Settings

Future Period Planning: Troubleshooting

Future Period Planning: Updating Projects

General Columns of the Activity Table

General Columns of the Assignments Table

General Columns of the EPS Table

Histogram Chart Settings Area

Level Resources Dialog Box (Reference)

Lists Columns of the Activity Table

Multiple Float Paths of the Activities Table

My Documents Portlet Toolbar

My Reviews Toolbar

My Workflows Toolbar

Number of Activities Columns of the EPS Table

Pages Supporting Filters

Percent Complete Columns of the Activity Table

Percent Complete Columns of the Assignments Table

Percent Complete Columns of the EPS Table

Performance Status Calculations

Personal Information Tab of the My Preferences Page

Pie Chart Settings Area

Portfolio Analysis Settings Area

Portfolio Analysis Toolbar

Portfolios Navigation Bar

Pre-response Thresholds (Risks)

Preferences Columns of the EPS Table

Private Documents Toolbar

Publication columns of the EPS Table

Recent Documents Toolbar

Resource Columns of the Assignments Table

Resources Navigation Bar

Risk Exposure (Pre-response)

Risk Exposure Calculations

Risk Scoring Method Description

Scorecard Settings Area

Set the Industry Type (P6 EPPM Only)

Standard Work Week Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Summary Columns of the EPS Table

Summary Tab of the View Calendar Dialog Box of the Activities Page, EPS Page, Assignments Page, or Resources Page

Team Member and P6 Mobile tab of the Consent Notice Page

Timesheet Feedback Columns of the Activity Table

Units Columns of the Activity Table

Units Columns of the Assignments Table

Units Columns of the EPS Table



Legal Notices | Your Privacy Rights
Copyright © 1999, 2024

Last Published Thursday, July 25, 2024