Overview
Use this detail window to assign and view activities that are impacted by the risk.
Note: You cannot edit activity information on this detail window.
Screen Elements
Activity ID field
The unique identifier of the activity.
In order to identify and track activities, P6 assigns each activity a unique Activity ID that is the result of joining the Activity ID Prefix with the Activity ID Suffix and then adding an Increment value.
For example, a prefix of PROJ-A#
combined with a suffix of 2500
and an Increment of 5
will yield the following activity IDs: PROJ-A#2500
, PROJ-A#2505
, etc.
Activity Name field
The name of the activity.
The activity name does not have to be unique.
Early Start field
The earliest possible date the remaining work for the activity can begin.
This date is calculated based on network logic, schedule constraints, and resource availability. Early start dates can change as the project progresses and as changes are made to the project management plan. If you schedule a project using Retained Logic this date will always be visible, even if an activity is completed.
Early Finish field
The earliest possible date the activity can finish. Early finish dates can change as the project progresses and changes are made to the project management plan.
This date is calculated based on network logic, schedule constraints, and resource availability. If you schedule a project using Retained Logic this date will always be visible, even if an activity is completed.
Getting Here
- Click Projects.
- On the Projects navigation bar, click Risks.
- On the Risks page, click the Activities detail window.