You can specify the default activity duration for new activities added in all projects.
- Choose Admin, Admin Preferences.
- Click the General tab.
- In the Activity Duration section, type a default activity duration in minutes, hours, days, weeks, months, or years.
Note
- If you change the default activity duration setting, the new default applies only to activities added after the change; existing activities are not affected.