Shift Calendar: Displays the resources shift calendar.
Shift: Type or click the arrows to enter the applicable shift number for which you are setting limits, if the shift calendar has more than one shift.
Effective Date: You can set varying limits and prices over time by specifying the effective start date for each change.
Max Units/Time: The number of units available during each workperiod (hour, day, week, or month) of the specified timeframe; you can enter a percentage, or a numeric value followed by a forward slash (/) and the appropriate time duration, depending on your user preference setting for time units.
Price/Unit: Double-click the cell, then type the resource's monetary price per unit. You can customize the columns to add additional price/unit fields.
When connected to a P6 Professional database: The columns display the names defined in the Admin Preferences dialog box for the rate types.
When connected to a P6 EPPM database: The columns display the names defined in the Application Settings in P6 for the rate types.
Add: Click to add additional limits.
Delete: Removes the selected limit.
Note
- You cannot mix unit types for a specific resource. For example, if there are five Price/Unit values defined for a resource, they must all be hours, or days, or weeks, etc. If there are multiple Price/Unit values defined for a resource and you change one of the units (e.g., from hours to days), the remaining units will all be changed. If you enter a price but not a unit, the default unit is hours.