Modifying a risk (P6 Professional Only)

Modify a risk by selecting the risk from the Risks view and editing applicable fields. After you modify a risk, the modifications apply to all activities assigned to the risk.

To modify a risk:

  1. Choose Project, Risks.
  2. Select the risk to modify.
  3. Display Risk Details.
  4. Click the applicable Details tab and make the changes.

    Notes:

    • If you select the value <None> for any Pre-Response field, all Response and Post-Response data is cleared.
    • If you select the value <None> for the Response Type field, all Post-Response values are cleared.