Calendars tab - Import Options dialog box

Use this tab to use, demote, or remove calendars and to rename calendars present in the XML file.

Basic Action section:

Global/Resource Calendars: Determines how global and resource calendars are imported.

Insert New: Retains data in the existing project and adds any new data items.

Keep Existing: Retains data in the existing project and does not overwrite it with the updated data or adds new data if the record does not exist and you have the appropriate security privileges.

Update Existing: Overwrites data in the existing project with updated data and adds new data if the record does not exist.

Do Not Import: Retains data in the existing project and does not import the updated data.

Advanced Actions section:

Name: Displays the name of the calendar in hierarchical form grouped by New and Saved. Data that is new in the XML file will be appear under New and data already saved in an the existing template will appear under Saved.

Type: Displays the type of calendar, Global or Resource.

Details: Displays the calendar's details.

Action: Determines if the calendar is imported, moved to a project, or removed.

New Name: The new name for the calendar.