Exchanging data with Oracle Primavera Cloud using Primavera Gateway (P6 EPPM Only)

If your Administrator has set up integration between P6 EPPM and Oracle Primavera Cloud, you can exchange data with Oracle Primavera Cloud for risk, task, work package, and scope integration.

To send data to Oracle Primavera Cloud:

  1. Open the project or projects that you want to exchange with Oracle Primavera Cloud.
  2. Select Exchange Data from the File Menu, and then select the menu option for sending data to Oracle Primavera Cloud.

To update the projects from Oracle Primavera Cloud:

  1. Open the project or projects that you want to exchange with Oracle Primavera Cloud.
  2. Select Exchange Data from the File Menu, and then select the menu option for updating data from Oracle Primavera Cloud.

    Notes:

    • You must have the Exchange Project Data with Oracle Primavera Cloud privilege set in P6 and P6 EPPM must be configured for integration with Oracle Primavera Cloud.
    • The process for updating from Oracle Primavera Cloud updates the WBS structure, including work packages for scope integration. This option also updates pre response and post response pessimistic dates for activities based on risk analysis in Oracle Primavera Cloud, even though you cannot see them in P6 Professional.
    • Do not modify the WBS structure, including WBS names and codes, once a project has been integrated with Oracle Primavera Cloud for scope management. Do not move activities between WBS nodes once a project has been integrated with Oracle Primavera Cloud for scope management