Activity tab - Modify Template dialog box

Import

Import milestones with resource assignments as: Choose to import milestones with associated resources as start milestone activities with associated expenses, or as task dependent activities with associated resource assignments.

Note

Import Microsoft Project's Task ID field to: Choose to import the Task ID field to P6 Professional's Activity ID field or a specified user defined text field.

Import Microsoft Project's fixed costs as expenses: Choose this option if you want to import Microsoft Project's fixed costs as expenses in P6 Professional. If you do not select this option, fixed costs are not imported.

Export

Export Activity ID to Microsoft Project's task field: Mark if you want to export P6 Professional's Activity ID field to a text field in Microsoft Project. Click the drop down arrow to select the Microsoft Project field.