Activity tab - Project Expense Details

Use this tab to specify the selected expense item's activity assignment and accrual type. You can also view the item's activity assignment according to work breakdown structure (WBS) element, activity status, and activity start and finish dates.

Activity Name: The name of the activity that incurs the selected expense. To select an activity, click .

WBS: The code for the WBS element that contains the selected expense's assigned activity.

Accrual Type: The rate at which the selected expense accrues, either as a lump sum at the activity's start or finish date, or uniformly over the duration of the activity. To select a type, click the down arrow.

Activity Status: The status of the activity that incurs the selected expense.

Activity Start: The start date or expected start date for the activity that incurs the selected expense.

Activity Finish: The finish date or expected finish date for the activity that incurs the selected expense.

Primary Resource: The primary resource for the activity that incurs the selected expense.