Add a resource curve

  1. Choose Enterprise, Resource Curves.
  2. Click Add.
  3. Select an existing curve from which to copy the curve value percentages, then click Select.
  4. Type a name for the new resource curve. You can type up to 60 alphanumeric characters. You must enter a resource curve name.
  5. Click Modify to define the curve's distribution. Edit the curve value percentages to create a curve that indicates how your costs/units should distribute over time. Curves are defined by 21 points (5% intervals from 0 to 100).
  6. Click Prorate to make the total of the distribution values equal to 100% while maintaining the shape you specified.
  7. Click OK, then click Close.