Calculate multiple float paths

When you schedule a project, you can choose to calculate multiple critical float paths.

  1. Choose Tools, Schedule.
  2. Click Options, then click the Advanced tab.
  3. Mark the Calculate multiple float paths option.
  4. Choose to calculate multiple paths using Total Float or Free Float.
  5. In the Display multiple float paths ending with activity field, click the Browse button to choose the activity on which you want the float paths to end.

    You can choose any activity; however, typically this activity is a milestone or some other major activity in the project schedule.
  6. Specify the number of float paths you want the module to calculate.

    Enter a low number (10 or less) to optimize performance.
  7. Click Close.

Notes

Related Topics

Analyzing the schedule using multiple critical float paths