Change successor relationships

  1. Choose Project, Activities.
  2. Select the activity whose successor relationship you want to change.
  3. Display Activity Details, then click the Successors or Relationships tab.
  4. To add a successor, click Assign in the Successor tab or in the Successors area of the Relationships tab. Select the successor activity you want to add.

    To change a relationship type, double-click the appropriate Relationship Type field, then select a new relationship type.

    To change a lag time value, double-click the appropriate Lag field, then enter a new time value.

    To remove a successor, in the Successor Activity column select the successor you want to remove, then click Remove.