Cut and paste activities in the Activity Table

  1. Select the activities you want to cut and paste.
  2. Choose Edit, Cut.
  3. Select the WBS band where you want to insert the cut activities, then choose Edit, Paste.

Note:

When connected to a P6 EPPM database: When you cut and paste activities within the same project, any associated risks from P6 are also moved; risks from P6 are not moved when you cut and paste activities to a different project.

When connected to a P6 Professional database: When you cut and paste activities within the same project, any associated risks are also moved; risks are not moved when you cut and paste activities to a different project.