Data tab - Project/Activity Usage Profile Options dialog box

Display

Cost: Choose to display the profile bars/curves in terms of costs.

Units: Choose to display the profile bars/curves in terms of units.

Display actual and earned value using financial period data: Mark to display past period actual values (rather than actual to date values) stored in financial period intervals for the Actual bar and curve, Planned Value curve, Earned Value curve, and Estimate at Completion curve. When you choose this option, stored past period actuals are distributed evenly, within each financial period, from the financial period start date to the financial period end date, and earned value calculations are based on these stored period quantities.

If you do not choose this option, the profile spreads actual to date values evenly from the actual start to the data date or actual finish date of the activity or assignment (unless you manually enter non-linear values when planning assignments to activities).

Tip:

Filter for Bars/Curves

Labor: Mark to display labor units or costs, depending on the selected display option, then select the fill pattern for displaying labor information.

Nonlabor: Mark to display nonlabor units or costs, depending on the selected display option, then select the fill pattern for displaying nonlabor information. You can select a new fill pattern.

Material: Mark to display material costs, depending on the selected display option, then select the fill pattern for displaying material information.

Expenses: Mark to display expense costs, then select the fill pattern for displaying expense information. The Expenses checkbox is available only if the selected display option is Cost.

Total: Mark to display total costs (Total = Labor + Nonlabor + Expenses). The Total checkbox is available only if the selected display option is Cost.

Note

Show Bars/Curves

Baseline: Mark to show primary baseline values by date for each time unit in the current layout, or show values cumulatively, as a horizontal curve. Click the Color button to select the color used to display baseline information.

Budgeted or Planned: (Activity Usage Profile only) Mark to show budgeted or planned values by date for each time unit in the current layout, or show values cumulatively, as a horizontal curve. Click the Color button to select the color used to display budgeted or planned values.

Actual: Mark to show actual values by date for each time unit in the current layout, or show values cumulatively, as a horizontal curve. Click the Color button to select the color used to display actual values.

Remaining Early: (Activity Usage Profile and Activity Profile only) Mark to show remaining early values by date for each time unit in the current layout, or show values cumulatively, as a horizontal curve. Click the Color button to select the color used to display remaining early values.

Remaining Late: (Activity Usage Profile and Activity Profile only) Mark to show remaining late values by date for each time unit in the current layout, or show values cumulatively, as a horizontal curve. Click the Color button to select the color used to display remaining late values.

Show Earned Value Curves

Planned Value Cost / Labor Units: Mark to show, as a curve, the portion of the budgeted or planned total cost or units scheduled to be completed as of the project data date.

Earned Value Cost / Labor Units: Mark to show, as a curve, the portion of the budgeted or planned total cost or units actually completed as of the project data date.

Estimate at Completion Cost (EAC) / Labor Units: Mark to show, as a curve, the estimated cost or units at completion.

Note

Related Topics

Manually enter future period assignment values