Define milestones

  1. Choose Project, Activities.
  2. Select the activity you want to define as a start or finish milestone.
  3. Display Activity Details, then click the General tab.
  4. In the Activity Type field, select Start Milestone or Finish Milestone.

Note

Related Topics

Display window details