Earned Value Cost

Earned Value Cost is the portion of the budgeted or planned  total cost of the activity that is actually completed as of the project data date. Computed as Earned Value Cost = Budget at Completion * Performance % Complete. The method for computing the performance percent complete depends on the earned-value technique selected for the activity's WBS.



Legal Notices | Your Privacy Rights
Copyright © 1999, 2023

Last Published Thursday, January 12, 2023