Enter monthly spending amounts

  1. Choose Enterprise, Projects, then select the EPS node/project for which you want to enter monthly spending amounts.
  2. Display Project Details, then click the Spending Plan tab.
  3. Type total expenditures for each month in the Spending Plan column.

    The Spending Plan Tally column shows any amounts previously recorded for lower-level project spending plans.

    The current variance is the difference between the monthly spending of the EPS node and its projects' tallies.

    You can type the benefit amount or profit portion of the monthly amounts; the benefit plan is also tallied.

Related Topics

Display window details



Legal Notices | Your Privacy Rights
Copyright © 1999, 2023

Last Published Thursday, January 12, 2023