Finish on or after constraint

A restriction you impose on an activity that limits the earliest time it can complete. The finish on or after constraint reduces float to coordinate parallel activities, ensuring that the finish of an activity is not scheduled before the specified date. It is usually applied to activities that have few predecessors that must finish before the next phase of a project.