Mandatory finish constraint

A restriction you impose on an activity that sets its early and late finish dates equal to the date you specify. The mandatory finish date is used regardless of its effect on network logic. This constraint affects the late dates for all activities that lead to the constrained activity and all early dates for the activities that lead from the constrained activity.