Mandatory start constraint

A restriction you impose on an activity that sets its early and late start dates equal to the date you specify. The mandatory early start date is used regardless of its effect on network logic. A mandatory early start date could affect the late dates for all activities that lead to the constrained activity and all early dates for the activities that lead from the constrained activity.