Budgeted or Planned Units: The expected number of units the selected resource/role assignment will use for the activity.

Budgeted or Planned Units/Time: The expected number of units the resource/role assignment is available during the workperiod.

Original or Planned Duration: The planned working time for the resource/role assignment on the activity.

Actual Units: The actual number of units worked by the resource/role on this activity.

Remaining Early Units: The remaining units of work to be performed by this resource/role assignment on this activity.

Remaining Units/Time: The units per time at which the resource/role will be performing work on the remaining portion of the activity.

Remaining Duration: The remaining working time for the resource/role assignment on the activity.