You can promote, or change, a project-level activity code and its values to a global or EPS-level activity code with global or EPS-level values.
- Choose Enterprise, Activity Codes.
- Choose Project, then click Modify.
- Select the code you want to promote, then click Make Global or Make EPS.
- Click Yes, then click Close.
Tip
- If you promote a project-level activity code and its values, your change applies to all activity assignments.