Replace resources assigned to activities

  1. Choose Project, Activities.
  2. Select the activity for which you want to replace a resource.
  3. Display Activity Details, then click the Resources tab.

    If resource security is enabled you can only view resources you have access to.
  4. Select the resource you want to replace.
  5. Click Add Resource.
  6. Click the Replace button in the Assign Resources dialog box.
  7. Select the new resource with which you want to replace the existing resource, then click the Assign button.
  8. Click the Close button.