Select Resources dialog box

Use the Select Resources dialog box to select specific resources for a leveling run.

Display Options bar: Click to change fonts and colors in this dialog box.

Level: Mark the checkbox beside each resource that you want to include in the leveling run. Clear the checkbox beside a resource if you do not want to include it in the leveling run.

Resource Code: Displays the resource name.

Max Units/Time: Shows the number of units the resource is available during each workperiod.

Select All: Click to select all resources in the list for the leveling run.

Clear All: Click to clear all of the checkboxes in the Level column.