Set global summarization options (P6 Professional Only)

In addition to specifying summarization options per project (Project Details, Settings tab), if you have administrator rights, you can specify global summarization options for storing resource spreads at the activity and resource levels.

  1. Choose Admin, Preferences.
  2. Select the Options tab.
  3. In the 'Select summarization periods' section, choose how you want to summarize and store resource data: By calendar, By financial period, or both.

    If you choose to summarize and store resource data by calendar intervals, in the WBS Level field, choose the time interval, such as week or month, for storing summarized activity data. Then, in the Resource/Role Assignment Level field, choose the time interval, such as week or month, for storing summarized resource data.

    If you choose to summarize and store resource data by financial period intervals, activity and resource data is stored in financial period intervals that correspond to the financial periods defined in the financial period calendars. Choosing this option enables P6 Professional to display all activity and resource data (including non-past period actual data) in financial period timescale intervals.

Tips:

Notes:

If no financial period calendars are defined, you can select the 'By financial period' option but data will not be summarized by financial period.

Related Topics

Set a project's summarization options