Specify the resource type for resources

  1. Choose Enterprise, Resources.
  2. Select the resource whose resource type you want to enter.
  3. Click the Details tab.
  4. To indicate that the selected resource performs labor, which is measured in units of time, choose Labor.
  5. To indicate that the selected resource does not perform labor, for example, if the resource is equipment, choose Nonlabor. The nonlabor resource is measured in units of time.
  6. To indicate that the selected resource is measured in units other than time, choose Material.

    If you selected Material as the resource type, select a unit of measure for the resource.

Note