Start on or after constraint

A restriction you impose on an activity that limits the earliest time it can begin. When calculating a schedule, the start on or after constraint is used in the forward pass only if the calculated early start date will be earlier than the imposed date. This constraint affects only early dates. The early start date of an activity with a start on or after constraint cannot be earlier than the imposed date, although the network logic may cause the early start to occur later.