Update Progress dialog box

Use the Update Progress dialog box to update the durations and actual values of the selected activities.

Current Data Date: Displays the current data date.

New Data Date: Select a new data date if the one show is not correct.

When using progress spotlight update progress for: Choose to update all of the highlighted activities that appear in the Gantt Chart or to update only selected activities.

When actuals are applied from timesheets, calculate activity remaining durations: Specify whether to recalculate the remaining duration based on the activity duration type or to always recalculate. If you choose to always recalculate, all activities are treated as Fixed Units and Fixed Units/Time.

Apply: Calculates and applies progress as follows and changes Current Data date to the New Data Date you specify.