Use date arithmetic

In the Modify Global Change dialog box, you can add or subtract a date from one another to calculate the number of workperiods between them, based on the activity or resource calendar. The following example find the difference between a baseline and the open project's start dates, based on the activity calendar:

30-Jul-02   -   27-Jul-02    = 3

Start         -   BL Start      = (User_number field)

You can add a number to a date to calculate a new (later) date, or subtract a number from a date to calculate a new

(earlier) date. For example,

27-Sep-02  +  3 =  30-Sep-02
27-Sep-02  -   3 =  30-Sep-02