EPS

Description: EPS.

Field

Type

Description

Read-Only

AnticipatedFinishDate

String

The anticipated finish date of the EPS. User-entered - not dependent upon any other fields. If there are no children, the anticipated finish date will be the finish date displayed in the columns.

No

AnticipatedStartDate

String

The anticipated start date of the EPS. User-entered - not dependent upon any other fields. If there are no children, the anticipated start date will be the start date displayed in the columns.

No

CreateDate

DateTime

The date this EPS was created.

Yes

CreateUser

String

The name of the user that created this EPS.

Yes

CurrentBudget

String

The sum of the original budget plus the approved and pending budgets from the budget change log.

Yes

CurrentVariance

String

The difference between the current budget and the total spending plan. Calculated as current budget - total spending plan. Not rolled up

Yes

DistributedCurrentBudget

String

The current budget values from one level lower.

Yes

FinishDate

String

The finish date of the EPS.

Yes

GUID

String

The globally unique ID generated by the system.

No

Id

String

The short code assigned to each EPS element for identification.

No

IndependentETCLaborUnits

String

The user-entered ETC total labor.

Yes

IndependentETCTotalCost

String

The user-entered ETC total cost.

Yes

LastSummarizedDate

String

The date the project was last summarized.

Yes

LastUpdateDate

DateTime

The date this EPS was last updated.

Yes

LastUpdateDate

String

The date this EPS was last updated.

Yes

LastUpdateUser

String

The name of the user that last updated this EPS.

Yes

LastUpdateUser

String

The name of the user that last updated this EPS.

Yes

Name

String

The name of the EPS element.

No

ObjectId

Int

The unique ID generated by the system.

No

OBSName

String

The name of the person/role in the organization, sometimes referred to as the "responsible manager".

Yes

OBSObjectId

String

The unique ID of the project manager from the project's OBS tree who is responsible for the EPS.

No

OriginalBudget

String

The original budget for the project.

No

ParentObjectId

ForeignKey

The unique ID of the parent EPS of this EPS in the hierarchy.

No

PlannedStartDate

String

The planned start date of the project. Used by the project scheduler.

Yes

ProjectObjectId

String

The internal Project ID of the EPS. This ID cannot be used to load a Project object directly.

Yes

ProposedBudget

String

The Proposed Budget, which is the sum of the original budget plus the approved and pending budgets from the budget change log.

Yes

SequenceNumber

String

The sequence number for sorting.

No

StartDate

String

The start date of the EPS.

Yes

SummaryAccountingVarianceByCost

String

the Planned Value minus the Actual Cost. A negative value indicates that the Actual Cost has exceeded the Planned Value.

Yes

SummaryAccountingVarianceByLaborUnits

String

the Planned Value Labor Units minus the Actual Units. Negative value indicates that Actual Units have exceeded the Planned Value Labor Units.

Yes

SummaryActivityCount

String

the number of activities that are currently in progress.

Yes

SummaryActualDuration

String

The actual duration.

Yes

SummaryActualExpenseCost

String

The actual costs for all project expenses associated with the EPS.

Yes

SummaryActualFinishDate

String

The latest actual finish date of all activities in the EPS.

Yes

SummaryActualLaborCost

String

The actual cost for all labor resources assigned to the activity.

Yes

SummaryActualLaborUnits

String

The actual labor units.

Yes

SummaryActualMaterialCost

String

The actual units for all material resources assigned to the activity.

Yes

SummaryActualNonLaborCost

String

The actual units for all nonlabor resources assigned to the activity.

Yes

SummaryActualNonLaborUnits

String

The actual nonlabor units.

Yes

SummaryActualStartDate

String

The earliest actual start date of all activities in the EPS.

Yes

SummaryActualThisPeriodCost

String

The actual this period cost (will be labor or nonlabor).

Yes

SummaryActualThisPeriodLaborCost

String

The actual this period labor cost

Yes

SummaryActualThisPeriodLaborUnits

String

The actual this period labor units.

Yes

SummaryActualThisPeriodMaterialCost

String

The actual this period material cost.

Yes

SummaryActualThisPeriodNonLaborCost

String

The actual this period nonlabor cost.

Yes

SummaryActualThisPeriodNonLaborUnits

String

The actual this period nonlabor units.

Yes

SummaryActualTotalCost

String

The actual labor cost + actual nonlabor cost + actual expense cost as of the project data date.

Yes

SummaryActualValueByCost

String

the actual total cost incurred on the activity as of the project data date, computed as Actual Labor Cost + Actual Nonlabor Cost + Actual Material Cost + Actual Expense Cost.

Yes

SummaryActualValueByLaborUnits

String

the actual total labor units for the activity as of the project data date (i.e., actual total cost by labor units).

Yes

SummaryAtCompletionDuration

String

The duration at completion.

Yes

SummaryAtCompletionExpenseCost

String

the sum of the actual plus remaining cost for all project expenses associated with the cost account.

Yes

SummaryAtCompletionLaborCost

String

The sum of the actual plus remaining costs for all labor resources assigned to the activity. Same as the planned labor costs if the activity is not started and the actual labor costs once the activity is completed.

Yes

SummaryAtCompletionLaborUnits

String

The sum of the actual plus remaining units for all labor resources assigned to the activity. Same as the planned labor units if the activity is not started and the actual labor units once the activity is completed.

Yes

SummaryAtCompletionMaterialCost

String

The material cost at completion. Same as the planned material costs if the activity is not started and the actual material costs once the activity is completed.

Yes

SummaryAtCompletionNonLaborCost

String

The nonlabor cost at completion. Same as the planned nonlabor costs if the activity is not started and the actual nonlabor costs once the activity is completed.

Yes

SummaryAtCompletionNonLaborUnits

String

The nonlabor units at completion. Same as the planned nonlabor units if the activity is not started and the actual nonlabor units once the activity is completed.

Yes

SummaryAtCompletionTotalCost

String

The estimated cost at completion for the activity. Note that the method for computing ETC depends on the earned-value technique selected for the activity's WBS.

Yes

SummaryAtCompletionTotalCostVariance

String

the Baseline Planned Total Cost - At Completion Total Cost.

Yes

SummaryBaselineCompletedActivityCount

String

The number of completed activities in the baseline.

Yes

SummaryBaselineDuration

String

Planned duration is the total working time from the activity current start date to the current finish date. Same as the actual duration plus the remaining duration. The total working time is computed using the activity's calendar.

Yes

SummaryBaselineExpenseCost

String

the planned cost for all project expenses associated with the activity in the primary baseline. Computed as the baseline actual expense cost plus the baseline remaining expense cost.

Yes

SummaryBaselineFinishDate

String

The current latest finish date of all activities in the EPS for the current baseline.

Yes

SummaryBaselineInProgressActivityCount

String

the number of activities that should be currently in progress, according to the primary baseline. Computed using the baseline start and finish dates and the current data date.

Yes

SummaryBaselineLaborCost

String

the planned cost for all labor resources assigned to the activity in the primary baseline. If no resources are assigned, computed as the activity Baseline Planned Labor Units * Project Default Price / Time.

Yes

SummaryBaselineLaborUnits

String

the planned units for all labor resources assigned to the activity in the primary baseline. Computed as the baseline actual labor units plus the baseline remaining labor units.

Yes

SummaryBaselineMaterialCost

String

the planned cost for all material resources assigned to the activity in the primary baseline. Computed from the baseline At Completion nonlabor units. If no resources are assigned.

Yes

SummaryBaselineNonLaborCost

String

the planned cost for all nonlabor resources assigned to the activity in the primary baseline. If no resources are assigned, computed as the activity Baseline Planned Nonlabor Units * Project Default Price / Time.

Yes

SummaryBaselineNonLaborUnits

String

the planned units for all nonlabor resources assigned to the activity in the primary baseline. Computed as the baseline actual nonlabor units plus the baseline remaining nonlabor units.

Yes

SummaryBaselineNotStartedActivityCount

String

The number of activities not started in the baseline.

Yes

SummaryBaselineStartDate

String

The current earliest start date of all activities in the EPS for the current baseline.

Yes

SummaryBaselineTotalCost

String

the Planned Total Cost for the activity in the primary baseline, including labor resources, nonlabor resources, and project expenses.

Yes

SummaryBudgetAtCompletionByCost

String

the Planned Total Cost through activity completion. Computed as Planned Labor Cost + Planned Nonlabor Cost + Planned Expense Cost, same as the Planned Total Cost.

Yes

SummaryBudgetAtCompletionByLaborUnits

String

the Baseline Labor Units

Yes

SummaryCompletedActivityCount

String

the number of activities that have an Actual Finish in the EPS.

Yes

SummaryCostPercentComplete

String

The percent complete of costs for the resource assignments in the EPS. Computed as Actual Units / At Complete Units * 100. Always in the range 0 to 100.

Yes

SummaryCostPercentOfPlanned

String

The activity actual cost percent of planned. The value can exceed 100. The baseline total cost is the activity's at completion cost from the current baseline.

Yes

SummaryCostPerformanceIndexByCost

String

the Earned Value divided by the Actual Cost. A value less than 1 indicates that the Actual Cost has exceeded the Planned Value.

Yes

SummaryCostPerformanceIndexByLaborUnits

String

the Earned Value Labor Units / Actual Labor Units.

Yes

SummaryCostVarianceByCost

String

the Earned Value minus the Actual Cost. A negative value indicates that the Actual Cost has exceeded the Planned Value.

Yes

SummaryCostVarianceByLaborUnits

String

the Earned Value Labor Cost minus Actual Value Labor Cost.

Yes

SummaryCostVarianceIndex

String

The value that is calculated as the Cost Variance divided by Earned Value.

Yes

SummaryCostVarianceIndexByCost

String

the Cost Variance divided by Earned Value.

Yes

SummaryCostVarianceIndexByLaborUnits

String

the Cost Variance Labor Units divided by Earned Value Labor Units.

Yes

SummaryDurationPercentComplete

String

The activity actual duration percent of planned. Computed as (baseline planned duration - remaining duration) / baseline planned duration * 100.

Yes

SummaryDurationPercentOfPlanned

String

The summary actual duration percent of planned of all activities under this EPS. Computed as actual duration / baseline duration * 100. The value can exceed 100. The Baseline duration is the activity's at complete duration from the current baseline.

Yes

SummaryDurationVariance

String

The duration between the activity's baseline duration and the at complete duration. Computed as baseline duration - at completion duration.

Yes

SummaryEarnedValueByCost

String

the Budget at Completion * Performance % Complete. The method for computing the Performance Percent Complete depends on the Earned Value technique selected for the activity's WBS. Budget at Completion is computed from the primary baseline.

Yes

SummaryEarnedValueByLaborUnits

String

the Schedule Variance Labor Units divided by the Planned Value Labor Units.

Yes

SummaryEstimateAtCompletionByCost

String

the Actual Cost plus the Estimate to Complete Cost. The method for computing Estimate to Complete depends on the Earned Value technique selected for the activity's WBS.

Yes

SummaryEstimateAtCompletionByLaborUnits

String

the Actual Labor Units + Estimate To Complete Labor Units. (Estimate To Complete Labor Units is calculated based off of the Earned Value setting on the EPS.)

Yes

SummaryEstimateAtCompletionHighPercentByLaborUnits

String

the high forecast of Estimate At Completion (EAC) by labor units.

Yes

SummaryEstimateAtCompletionLowPercentByLaborUnits

String

the low forecast of Estimate At Completion (EAC) by labor units.

Yes

SummaryEstimateToCompleteByCost

String

the Remaining Total Cost for the activity or the Performance Factor * (Budget at Completion - Earned Value), depending on the Earned Value technique selected for the activity's WBS (calculated from the primary baseline).

Yes

SummaryEstimateToCompleteByLaborUnits

String

The estimated quantity to complete the activity.

Yes

SummaryExpenseCostPercentComplete

String

The percent complete of cost for all expenses associated with the EPS. It is computed as Actual Expense Cost / At Complete Expense Cost * 100, and it is always in the range of 0 to 100.

Yes

SummaryExpenseCostVariance

String

the Baseline Planned Expense Cost - At Completion Expense Cost (At Completion Expense Cost = Actual Expense Cost + Remaining Expense Cost).

Yes

SummaryFinishDateVariance

String

The duration between the finish date in the current project and the baseline finish date. Calculated as finish date - baseline finish date.

Yes

SummaryInProgressActivityCount

String

The number of activities that are currently in progress.

Yes

SummaryLaborCostPercentComplete

String

The percent complete of cost for all labor resources assigned to the EPS. It is computed as Actual Labor Cost / At Complete Labor Cost * 100, and it is always in the range of 0 to 100.

Yes

SummaryLaborCostVariance

String

the Baseline Planned Labor Cost - At Completion Labor Cost.

Yes

SummaryLaborUnitsPercentComplete

String

The percent complete of units for all labor resources for the EPS. Computed as actual labor units / at complete labor units * 100. Always in the range 0 to 100.

Yes

SummaryLaborUnitsVariance

String

The difference between baseline labor units and at completion labor units. Calculated as Baseline labor units - at completion labor units.

Yes

SummaryMaterialCostPercentComplete

String

The percent complete of cost for all material resources assigned to the EPS. It is computed as Actual Material Cost / At Complete Material Cost * 100, and it is always in the range of 0 to 100.

Yes

SummaryMaterialCostVariance

String

The variance that is calculated as Baseline Material Cost - At Completion Material Cost.

Yes

SummaryNonLaborCostPercentComplete

String

The percent complete of cost for all non-labor resources assigned to the EPS. It is computed as Actual Nonlabor Cost / At Complete Nonlabor Cost * 100, and it is always in the range of 0 to 100.

Yes

SummaryNonLaborCostVariance

String

The Baseline Planned Nonlabor Cost - At Completion Nonlabor Cost.

Yes

SummaryNonLaborUnitsPercentComplete

String

The percent complete of units for all nonlabor resources for the EPS. Computed as Actual Nonlabor Cost / At Completion Nonlabor Cost * 100. Always in the range 0 to 100.

Yes

SummaryNonLaborUnitsVariance

String

The difference between baseline nonlabor units and at completion non labor units. Calculated as Baseline nonlabor units - at completion nonlabor units.

Yes

SummaryNotStartedActivityCount

String

the number of activities that are currently not started.

Yes

SummaryPerformancePercentCompleteByCost

String

the percent complete of performance for all labor resources, nonlabor resources, and expenses. Computed as Earned Value / Budget At Completion * 100. Always in the range 0 to 100.

Yes

SummaryPerformancePercentCompleteByLaborUnits

String

the percent complete of performance for all labor resources. Computed as earned value labor units / baseline labor units * 100. Always in the range 0 to 100.

Yes

SummaryPlannedCost

String

The sum of all planned expense, non labor, labor, and material costs in the EPS.

Yes

SummaryPlannedDuration

String

The total working days between planned start and finish dates in the EPS.

Yes

SummaryPlannedExpenseCost

String

The sum of all planned expense costs in the EPS.

Yes

SummaryPlannedFinishDate

String

The latest planned finish date of all activities in the EPS.

Yes

SummaryPlannedLaborCost

String

The sum of all planned labor costs in the EPS.

Yes

SummaryPlannedLaborUnits

String

The sum of all planned labor units in the EPS.

Yes

SummaryPlannedMaterialCost

String

The sum of all planned material costs in the EPS.

Yes

SummaryPlannedNonLaborCost

String

The sum of all planned non labor costs in the EPS.

Yes

SummaryPlannedNonLaborUnits

String

The sum of all planned non labor units in the EPS.

Yes

SummaryPlannedStartDate

String

The earliest planned start date of all activities in the EPS.

Yes

SummaryPlannedValueByCost

String

The Budget at Completion * Schedule % Complete. The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Budget at Completion is computed from the primary baseline

Yes

SummaryPlannedValueByLaborUnits

String

The portion of the baseline labor units that is scheduled to be completed as of the project data date. The Baseline Labor Units is taken from the current baseline.

Yes

SummaryProgressFinishDate

String

the date the activity is expected to be finished according to the progress made on the activity's work products. The expected finish date is entered manually by people familiar with progress of the activity's work products.

Yes

SummaryRemainingDuration

String

The total working time from the EPS remaining start date to the remaining finish date.

Yes

SummaryRemainingExpenseCost

String

The remaining costs for all project expenses associated with the activities in the EPS.

Yes

SummaryRemainingFinishDate

String

The date the resource is scheduled to finish the remaining work for the activity. Before the activity is started, the remaining finish date is the same as the planned finish date.

Yes

SummaryRemainingLaborCost

String

The remaining costs for all labor resources assigned to the activities. The remaining cost reflects the cost remaining for the EPS.

Yes

SummaryRemainingLaborUnits

String

The remaining units for all labor resources assigned to the activities. The remaining units reflects the work remaining to be done for the EPS.

Yes

SummaryRemainingMaterialCost

String

The remaining material costs for all project expenses associated with the activities in the EPS.

Yes

SummaryRemainingNonLaborCost

String

The remaining nonlabor costs for all project expenses associated with the activities in the EPS.

Yes

SummaryRemainingNonLaborUnits

String

The remaining units for all nonlabor resources assigned to the activities. The remaining units reflects the work remaining to be done for the EPS.

Yes

SummaryRemainingStartDate

String

The earliest remaining start of all activities assigned to the EPS.

Yes

SummaryRemainingTotalCost

String

The sum of all remaining total costs in the EPS.

Yes

SummarySchedulePercentComplete

String

The measure that indicates how much of the EPS baseline duration has been completed so far. Indicative of how much of the EPS duration should be currently completed, relative to the selected baseline.

Yes

SummarySchedulePercentCompleteByLaborUnits

String

the percent complete of units for all labor resources. Computed as Actual Labor Units / At Completion Labor Units * 100. Always in the range 0 to 100.

Yes

SummarySchedulePerformanceIndexByCost

String

the Earned Value divided by the Planned Value. A value less than 1 indicates that less work was actually performed than was scheduled.

Yes

SummarySchedulePerformanceIndexByLaborUnits

String

the Earned Value Labor Units divided by Planned Value Labor Units.

Yes

SummaryScheduleVarianceByCost

String

the Earned Value divided by the Planned Value. A negative value indicates that less work was actually performed than was scheduled.

Yes

SummaryScheduleVarianceByLaborUnits

String

the Earned Value Labor Units minus the Planned Value Labor Units.

Yes

SummaryScheduleVarianceIndex

String

The value that is calculated as the Schedule Variance Labor Units divided by Planned Value Labor Units.

Yes

SummaryScheduleVarianceIndexByCost

String

the Schedule Variance divided by the Planned Value.

Yes

SummaryScheduleVarianceIndexByLaborUnits

String

the Schedule Variance Labor Units divided by the Planned Value Labor Units.

Yes

SummaryStartDateVariance

String

The duration between the start date in the current project and the baseline start date. Calculated as start date - baseline start date.

Yes

SummaryToCompletePerformanceIndexByCost

String

the (Budget at Completion - Earned Value) divided by (Estimate at Completion - Actual Cost).

Yes

SummaryTotalCostVariance

String

The value that is calculated as baseline total cost - total cost.

Yes

SummaryTotalFloat

String

The amount of time the EPS can be delayed before delaying the project finish date. Total float can be computed as late start - early start or as late finish - early finish; this option can be set when running the project scheduler.

Yes

SummaryUnitsPercentComplete

String

The percent complete of units for the resource assignments in the EPS. Computed as Actual Units / At Complete Units * 100. Always in the range 0 to 100.

Yes

SummaryVarianceAtCompletionByLaborUnits

String

the Baseline Planned Total Labor Units minus Estimate at Completion Labor Units.

Yes

TotalBenefitPlan

String

The sum of the monthly benefit plan.

Yes

TotalBenefitPlanTally

String

The sum of the monthly benefit plan tally.

Yes

TotalFunding

String

The total amount of funding contributed to the project by your funding sources.

Yes

TotalSpendingPlan

String

The sum of the monthly spending plan.

Yes

TotalSpendingPlanTally

String

The sum of the monthly spending plan tally.

Yes

UnallocatedBudget

String

The total current budget minus the distributed current budget.

Yes

UndistributedCurrentVariance

String

The total spending plan minus the total spending plan tally.

Yes