CBSResourceSpread

Description: Summarized spread data per CBS per resource assignment.

Field

Type

Description

Read-Only

ActualCost

Double

Actual Cost of the resource assignments when summarized by CBS

No

ActualUnits

Double

The actual units of the resource assignments when summarized by CBS

No

AtCompletionCost

Double

At Completion cost of the resource assignments when summarized by CBS

No

AtCompletionUnits

Double

At Completion units of the resource assignments when summarized by CBS.

No

BaselineType

String

The name of the baseline type for this project baseline. Baseline types are used to categorize project baselines.

No

CBSObjectId

ForeignKey

The unique ID of CBS.

Yes

CurrencyId

String

Currency Id

No

CurrencyName

String

Currency Name

No

DataDate

DateTime

The data date of the project when it was last summarized by CBS.

No

EndDate

DateTime

End date of the resource assignments when summarized by CBS

No

ObjectId

String

The unique ID generated by the system.

No

OriginalProjectObjectId

ForeignKey

The original object id of the associated Project

Yes

PlannedCost

Double

Planned cost of the resource assignments when summarized by CBS

No

PlannedUnits

Double

The planned units of the resource assignments when summarized by CBS.

No

ProjectId

String

The short code that uniquely identifies the project.

Yes

ProjectName

String

The name of the associated project.

Yes

ProjectObjectId

ForeignKey

The unique ID of the associated project.

Yes

RemainingCost

Double

Remaining cost of the resource assignments when summarized by CBS

No

RemainingUnits

Double

The remaining units of the resource assignments when summarized by CBS

No

ResourceId

String

The short code that uniquely identifies the resource.

Yes

ResourceName

String

The name of the resource.

Yes

ResourceType

String

The resource type: "Labor", "Nonlabor", or "Material".

No

StartDate

DateTime

Start date of the resource assignments when summarized by CBS

No

SummaryActualCost

Double

Actual cost of the resource assignments when summarized by CBS

Yes

SummaryActualFinish

DateTime

Actual finish date of the resource assignments when summarized by CBS

Yes

SummaryActualStart

DateTime

Actual Start date of the resource assignments when summarized by CBS

Yes

SummaryActualUnits

Double

Actual Units of the resource assignments when summarized by CBS

Yes

SummaryAtCompletionCost

Double

At completion cost of the resource assignments when summarized by CBS

Yes

SummaryAtCompletionUnits

Double

At Completion Units of the resource assignments when summarized by CBS

Yes

SummaryPlannedCost

Double

Planned cost of the resource assignments when summarized by CBS

Yes

SummaryPlannedFinish

DateTime

Finish date of the resource assignments when summarized by CBS

Yes

SummaryPlannedStart

DateTime

Planned start of the resource assignments when summarized by CBS

Yes

SummaryPlannedUnits

Double

Planned Units of the resource assignments when summarized by CBS

Yes

SummaryRemainingCost

Double

Remaining cost of the resource assignments when summarized by CBS

Yes

SummaryRemainingFinish

DateTime

Remaining finish date of the resource assignments when summarized by CBS

Yes

SummaryRemainingStart

DateTime

Remaining Start date of the resource assignments when summarized by CBS

Yes

SummaryRemainingUnits

Double

Remaining Units of the resource assignments when summarized by CBS

Yes

UnitAbbreviation

String

Unit Abbreviation

No

UnitName

String

Unit Name

No