CBSTemplateCode

Description: The list of all CBS codes defined at the workspace level part of a Workspace CBS

Field

Type

Description

Read-Only

ActualCostToDate

Double

The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done).

No

ActualHoursToDate

Double

The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done). This is the cumulative value for all objects in the workspace with the same CBS code.

No

AdjustedCost

Double

The amount the scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.

No

ApprovedChangedCost

Double

The sum of all approved cost changes in the change records for the scope assignment.

No

ApprovedChangedHours

Double

The sum of all approved change hours in the change and transfer records for the scope assignment. This is the cumulative value for all objects in the workspace with the same CBS code.

No

AtCompletionCost

Double

The total cost at the completion of the scope assignment.Calculated as Revised Cost plus Adjusted Cost.

No

AtCompletionHours

Double

The total hours expected for the scope assignment.Calculated as Revised Hours plus Adjusted Hours. This is the cumulative value for all objects in the workspace with the same CBS code.

No

BACCost

Double

The Revised Cost or At Completion Cost at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Cost of the current project if no baseline is set.

No

BACHours

Double

The Revised Hours or At Completion Hours at the time the current baseline was set. This is the cumulative value for all objects in the workspace with the same CBS code.

No

BaselineCost

Double

The Revised Cost at the time the current baseline was set.

No

BaselineHours

Double

The Revised Hours at the time the baseline was set. This is the cumulative value for all objects in the workspace with the same CBS code.

No

CBSCode

String

The code value of the CBS code. The code may have one or more segments according to the segment definition.

No

cbsTemplateObjectId

ForeignKey

The unique identifier for the CBS template.

No

CopiedFromObjectId

ForeignKey

The unique identifier of the CBSTemplateCode.

No

CostType

Enum

The category of the cost breakdown structure code. Expense: Represents an expense. Capital: Represents capital. None: Type is not divided into expense or capital.None is selected by default if no other choice is made.

No

CurrentBudget

Double

The total approved current manual budget of a project. Calculated as the sum of Approved Original Manual Budget plus Approved Manual Budget Changes plus Approved Manual Budget Transfers.

No

CurrentBudgetWorkspace1

Double

Workspace current budget.

No

CurrentBudgetWorkspace2

Double

Workspace current budget.

No

CurrentBudgetWorkspace3

Double

Workspace current budget.

No

Description

String

The name of the CBS Code.

No

EACCost

Double

Calculated as ETC Cost plus Actual Cost to Date.

No

EACHours

Double

Calculated as ETC Hours plus Actual Hours to Date. This is the cumulative value for all objects in the workspace with the same CBS code.

No

EarnedCost

Double

Calculated as Performance Percent Complete multiplied by BAC Cost.

No

EarnedHours

Double

Calculated as Performance Percent Complete multiplied by BAC Hours. This is the cumulative value for all objects in the workspace with the same CBS code.

No

ETCAdjustedHours

Double

The amount of scope assignment work that is not yet accounted for. This is the cumulative value for all objects in the workspace with the same CBS code.

No

ETCCost

Double

The estimate of the cost needed to complete the work.Calculated as BAC Cost minus Earned Cost.

No

ETCHours

Double

The estimated number of hours needed to complete the work. Calculated as BAC Hours minus Earned Hours. This is the cumulative value for all objects in the workspace with the same CBS code.

No

InstalledCost

Double

The total cost incurred on the scope assignment as of the current date.

No

InstalledHours

Double

Hours spent on the scope assignment. Calculated as Installed Quantity multiplied by Revised Productivity Rate. This is the cumulative value for all objects in the workspace with the same CBS code.

No

IsActive

Boolean

The active field indicates whether the CBS code is active for use.

No

IsCodeCopied

Boolean

The flag represents is templateCode copied or not

No

IsTotalRow

Boolean

Indicates this item represents the total cost of the project.

No

ObjectId

String

The unique ID generated by the system.

No

ParentObjectId

ForeignKey

The unique identifier of the parent CBS.

No

PendingChangedCost

Double

Calculated as the sum of all pending cost changes in the change records for the scope assignment.

No

PendingChangedHours

Double

Calculated as the sum of all pending hour changes in the change records for the scope assignment. This is the cumulative value for all objects in the workspace with the same CBS code.

No

PlannedCost

Double

The original cost of the scope assignment.

No

PlannedHours

Double

The original expected hours needed to complete all the work required to install the material quantity on the scope assignment. This is the cumulative value for all objects in the workspace with the same CBS code.

No

ProjectActualCost

Double

Total cost accrued on a project within a given time period. The Actual Cost data is only available when the application is connected with P6 EPPM and is not editable.

No

ProjectActualHours

Double

The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).

No

ProjectCPI

String

The measure of a project's cost efficiency.A value of less than 1 indicates the project is over budget, while a value greater than 1 indicates the project is under budget.

No

ProjectEarnedCost

Double

The value of work performed on a project in reference to the approved budget for the project. The cost value used for the Earned Value Management of a project.

No

ProjectEarnedHours

Double

Calculated as Performance Percent Complete multiplied by BAC Hours.

No

ProjectHPI

Double

Calculated as the total of Project Earned Hours divided by Project Actual Hours.

No

PushDownStatus

Boolean

The push down status of a cbs template code. May be manual or automatic.

No

RemainingCost

Double

The amount left to be spent.If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate.

No

RemainingHours

Double

The number of hours left for the scope assignment. Calculated as Remaining Quantity multiplied by Revised Productivity Rate. This is the cumulative value for all objects in the workspace with the same CBS code.

No

RevisedCost

Double

The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost.

No

RevisedHours

Double

Original Hours before the baseline is set. After the baseline is set, Revised Hours is equal to Original Hours plus Approved Change Hours. This is the cumulative value for all objects in the workspace with the same CBS code.

No

SequenceNumber

String

The CBS template item sequence number.

No

WorkspaceCode

String

The user-specified identifier of the workspace.

No