Description: CBS Sheet Row fields.
Field | Type | Description | Read-Only |
---|---|---|---|
ActualHoursToDate | Double | The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done). | No |
ApprovedChangedHours | Double | The sum of all approved change hours in the change and transfer records for the scope assignment. | No |
AtCompletionHours | Double | The total hours expected for the scope assignment. | No |
BACHours | Double | The Revised Hours or At Completion Hours at the time the current baseline was set, depending on the selection for the Budget At Completion Method. | No |
BaselineHours | Double | The Revised Hours at the time the baseline was set. | No |
EACHours | Double | Calculated as ETC Hours plus Actual Hours to Date. This is the cumulative value for all objects in the project with the same CBS code. | No |
EarnedHours | Double | Calculated as Performance Percent Complete multiplied by BAC Hours. | No |
ETCAdjustedHours | Double | The amount of scope assignment work that is not yet accounted for. | No |
ETCHours | Double | The estimated number of hours needed to complete the work. | No |
InstalledHours | Double | Hours spent on the scope assignment. | No |
ObjectId | Double | The unique ID generated by the system. | No |
PendingChangedHours | Double | Calculated as the sum of all pending hour changes in the change records for the scope assignment. | No |
PlannedHours | Double | The original expected hours needed to complete all the work required to install the material quantity on the scope assignment. | No |
ProjectActualHours | Double | The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done). | No |
ProjectEarnedHours | Double | Calculated as Performance Percent Complete multiplied by BAC Hours. | No |
ProjectHPI | Double | Calculated as the total of Project Earned Hours divided by Project Actual Hours. | No |
RemainingHours | Double | The number of hours left for the scope assignment. | No |
RevisedHours | Double | Original Hours before the baseline is set. After the baseline is set, Revised Hours is equal to Original Hours plus Approved Change Hours. | No |