Synchronize Project Actual Cost & progress from P6 to Primavera Cloud

This project data field-mapping template that transfers a Project business object between P6 and Gateway. Use this template when a P6 project is in the execution phase, progress data such as Actual cost, schedule percent complete and dates are transferred to Primavera Cloud.

The following fields are mapped for each Project business object:

Primavera Cloud

Gateway

P6

projectName

Name

Name

description

Description

Description

status

Status

Status

manager

Owner

OwnerResourceId

actualStartDate

ActualStartDate

SummaryActualStartDate

actualFinishDate

ActualFinishDate

SummaryActualFinishDate

actualCost

ActualCost

SummaryActualTotalCost

percentComplete

PercentComplete

SummarySchedulePercentComplete

projectCode

Id

Id