This project field-mapping template pulls planned total cost data in the WBSSpread business objects from P6 to Primavera Cloud. All necessary spread field mappings should be included as well. i.e. period start or finish dates. This is documented to just include the specific cost spread mapped from P6 to Primavera Cloud.The following fields are mapped in the template:
Primavera Cloud | Gateway | P6 |
---|---|---|
PeriodType | PeriodType | PeriodType |
StartDate | StartDate | StartDate |
EndDate | EndDate | EndDate |
PlannedTotalCost | PlannedTotalCost | PlannedTotalCost |